Repainting and retrofitting - TPS E-Hub 2

Repainting of TPS
27 October 2009 - 30 October 2009: Washing Works at South Block
31 October 2009 - 14 November 2009: Repainting Works at South Block
4 November 2009 - 7 November 2009: Washing Works at Boris Johnston Block
8 November 2009 - 20 November 2009: Repainting Works at Boris Johnston Block
9 November 2009 - 13 November 2009: Washing Works at North Block
14 November 2009 - 26 November 2009: Repainting Works at North Block
16 November 2009 - 20 November 2009: Washing Works at Green Block
21 November 2009 - 2 December 2009: Repainting Works at Green Block
25 November 2009 - 29 November 2009: Washing Works at West Block
30 November 2009 - 7 December 2009: Repainting Works at West Block
Green - Already Done
Blue - Undergoing Repaint
Rules & Regulations
Do not touch the railings that are painting and for safety reason, do not meddle with the safety life line, sling and platform of the gondola
2009 - Changes
Repainting & Retrofitting of Tampines Primary School (Bedok Campus) Successful, Voted 100%.

Tuesday, March 15, 2011

Repainting and retrofitting - TPS E-Hub

Included in the repainting project -
Repainting of the school
These can only be done during non-school hours to minimise disruption.
Install shelter-cover at the walkway
Installation of covered end next to the drain to prevent rain from coming in.
Install sheltered walkways
Repainting of the railings
Install additional CCTV cameras
Replacement of all Notice Boards, including those damaged glasses happened in fire drill.
Install new signage (Completed)
Repainting of the wall
Projects (Earlier)
Repainting of Tampines Primary School
Repainting of interior walls
Covering of the walls on the corridors
Installation of new signage
Repainting of the preserved wall